Automatic meter reading installation for MEPCO domestic consumers

Life in Pakistan

How to Apply for a New Electricity Connection in Pakistan: DocumentsDemand Notice and Meter

A practical guide to applying through your distribution company or K-Electric, paying the demand notice and getting the meter installed.

enc.com.pk for most distribution companiesOnline portal
Apply to K-Electric online or at a Customer Care CentreKarachi
Energisation within 15 days if all prerequisites are metK-Electric target
The demand notice, paid at a bankKey payment

The Quick Answer

To get a new electricity connection in Pakistan you apply to the company that supplies your area. Outside Karachi that is a distribution company (DISCO) such as LESCO, IESCO, FESCO, GEPCO or MEPCO. In Karachi it is K-Electric. You submit your CNIC, proof that you own or lawfully occupy the property and the other documents the company asks for. The company checks the papers, surveys the site and issues a demand notice. You pay the demand notice at a bank, and after payment the company installs and energises the meter.

The Power Division's own guidance says you can apply online through the Electricity New Connection (ENC) portal at enc.com.pk, and K-Electric runs its own online application and Customer Care Centres. Fees, documents and waiting times are changed by the companies and the regulator from time to time. This page explains the general process and tells you where to check the current requirement.

Who Supplies Your Area

Pakistan's electricity is distributed by several companies, each with its own territory. The distribution companies include LESCO (Lahore area), IESCO (Islamabad and Rawalpindi area), FESCO (Faisalabad area), GEPCO (Gujranwala area), MEPCO (Multan area), PESCO (Peshawar area), HESCO (Hyderabad area), SEPCO (Sukkur area) and QESCO (Quetta area), along with others. K-Electric supplies Karachi and nearby areas. Your latest electricity bill shows the company name. If you have no bill because the house is new, ask neighbours, or search for your area on the company website.

The Power Division says the ENC portal directs your application to the relevant company, so you do not have to work out the right office yourself. K-Electric applications are separate and go through the K-Electric website or app. If you are a tenant, our page on renting a home in Pakistan explains why you will usually need the owner's permission.

If you are moving into a new home, you may also need a gas supply: see how to get a new gas connection. Some owners now plan solar at the same time, and our guide to solar panel sizing for Pakistani homes helps you work out the size of a system.

Documents You Are Likely to Need

The exact list depends on the company, the type of connection (domestic, commercial, industrial) and the load. These are the documents that official pages and recent reports mention most often.

Your CNIC

An attested copy of the applicant's CNIC is standard. Our guide to the CNIC explains how to get or renew one. Some companies also ask for the CNICs of witnesses, although an older guide said this was not required for single-phase meters.

Proof of ownership

This can be a registered deed, a transfer letter, an allotment letter or another recognised document. K-Electric lists many accepted forms, including lease, mutation, allotment, conveyance or sale deed, and gift deed. See property registration and transfer for what those documents are.

Tenant's papers

If you are a tenant, expect to need a no objection certificate (NOC) from the owner on stamp paper, signed before an oath commissioner, plus the tenancy agreement.

Affidavit on stamp paper

Companies often ask for an affidavit that the property has no other connection and no outstanding dues. K-Electric asks for a standard affidavit on Rs 200 stamp paper, attested by a notary public or oath commissioner. Stamp paper is now bought online in several provinces.

Wiring test report

Reports from October 2025 said LESCO would require a test report verified online by an Electric Inspector before issuing a demand notice. In Karachi, K-Electric asks for an electrical inspector test form. Ask your electrician to arrange this early.

Tax documents for business use

K-Electric asks for an NTN certificate or Active Taxpayer List status for commercial and industrial connections.

How to Apply Through a Distribution Company (DISCO)

The process below is the one described by the Power Division and recent reports. Individual companies may add steps, so follow the screens on the portal.

  1. Open the application. Go to enc.com.pk or the New Connection section of your company's website and choose your distribution company.
  2. Fill in the form. Enter your CNIC, the type of connection, the load you need and the address of the premises.
  3. Upload your documents as clear scans. Unclear scans are a common cause of delay.
  4. Submit, then keep your tracking details. Save the application number.
  5. Hand over hard copies if asked. The Power Division says a company representative collects hard copy documents during the site survey. Some offices still ask for a printed form with attached documents.
  6. Wait for verification and survey. The company checks the papers and the site, including distance to the nearest pole and transformer capacity.
  7. Receive the demand notice. If approved, you receive a demand notice stating what you must pay.
  8. Pay at the designated bank and keep the receipt. Send or show a copy if the office asks.
  9. Meter installation. After payment is confirmed, the company supplies the meter and materials, installs them and switches on supply.

Never pay anyone in cash on the promise of a faster connection. Official channels give you a demand notice and a bank challan.

Electricity meters for domestic consumers under an automatic meter reading project of MEPCO
Meters installed for domestic electricity consumers under an automatic meter reading project of MEPCO.

How to Apply in Karachi With K-Electric

K-Electric accepts applications through its website, the KE Live app and its Customer Care Centres. Its published guidance describes this sequence.

  1. Apply and upload documents. You receive a provisional case ID by SMS from 8119, and login details by SMS and email.
  2. Case ID is registered after your documents are verified.
  3. Site survey. K-Electric says the survey is done within about three to four working days of the case ID. The estimate follows, generated within about five days.
  4. Pay the estimate and refundable security deposit online or at partner banks. The estimate is valid for 30 days from the case ID, and an expired estimate can be reissued on request.
  5. Submit the electrical inspector (EIK) test form if required, then the connection is energised.

K-Electric states that a new connection should be energised within 15 days, and an automatic meter reading (AMR) meter within 20 days, if all prerequisites are met. It also publishes longer expected timelines for larger loads, for example a total of 30 days for loads up to 15 kW and 44 days for 16 to 70 kW. K-Electric also says its employees are not allowed to collect cash for any service. Concerns can be reported to [email protected].

K-Electric Published Timelines by Load

These figures come from K-Electric's own guide and are estimates in days, not guarantees.

Load categorySurveyEstimateMaterialInstallationTotal
Up to 15 kW4611930
16 to 70 kW4625944
71 to 500 kW57361058
501 to 5,000 kW10205521106

What It Costs and What the Demand Notice Is

The demand notice is not your monthly bill. It is a one-time payment document that can cover a security deposit, service connection charges and the cost of the meter or line materials. The amount depends on your load, whether you need a single-phase or three-phase meter, whether the property is urban or rural and how far you are from the existing pole.

The Power Division gives a sample calculation for a house 80 metres from an existing pole. For a 3 kW single-phase connection, it shows a material cost of Rs 12,000 plus a security deposit of Rs 3,660 for an urban area. For a 5 kW three-phase connection, it shows Rs 25,400 plus Rs 6,100. These are illustrative and undated, so do not treat them as today's price. News reports in 2024 quoted an estimated Rs 7,240 for a single-phase LESCO meter, but also said some Lahore sub-divisions were charging Rs 18,000 to Rs 25,000 during a meter shortage. In October 2025, LESCO was reported to be allowing consumers to buy approved single-phase meters in the market with a LESCO NOC, after which a demand notice is issued.

The safe rule is to pay only the amount stated on an official demand notice, and only through the bank challan. If the amount looks very high, ask the sub-division in writing why, and ask for a breakdown.

NEPRA approved a revised Consumer Service Manual for all distribution companies in November 2025, according to K-Electric, and it contains an annexure on the time frame for new connections. The manual is on the NEPRA website. Charges and timelines can differ by company and by load, so rely on the demand notice you receive.

After You Pay: Meter, First Bill and Solar

Once the bank confirms your payment, the company installs the meter and the service line. Make sure the premises are accessible and the wiring is ready, otherwise the visit is wasted. K-Electric says the first bill is issued within 45 to 60 days of connection. Our page on how to check electricity and gas bills shows how to look up and pay bills online.

If you plan to install solar panels, ask about net metering before you finalise your load. Our guide to load shedding, net metering and solar explains the basics. Rules for net metering and net billing have been changing, and K-Electric publishes its own guidelines, so check with your company before you buy equipment.

An automatic meter reading device for a domestic electricity consumer
An automatic meter reading device installed for a domestic electricity consumer.

Common Reasons for Delay and Rejection

  • Unpaid dues. Outstanding bills on a previous meter at the same premises can block a new connection. K-Electric lists this as a common reason for rejection.
  • Incomplete or unclear documents. Wrong names, unclear scans and missing attestation are frequent causes.
  • Property still under construction or merged plots without a clear division.
  • Name mismatch. The owner's name on the documents should match your application. If the name is different, you may need proof of transfer.
  • Unpaid or expired demand notice or estimate. Pay on time, as an expired notice can delay the file.
  • Access denied for the survey or an unreachable phone number.
  • Meter shortages, which have delayed some DISCOs in the past.

Official Sources and Where to Get Help

  • Applications: the Electricity New Connection portal (enc.com.pk), as listed by the Power Division, or the New Connection section of your company's website. K-Electric applicants should use the K-Electric website or app.
  • Bills and non-delivery complaints: the Power Division lists bill.pitc.com.pk for bills and the CCMS portal for bill non-delivery complaints. For billing errors or tariff disputes, contact your sub-division, complaint centre or customer service centre.
  • Unresolved complaints: the regulator, NEPRA (nepra.org.pk), publishes decisions on consumer complaints against distribution companies and K-Electric. We could not confirm the current filing steps, so check its website.
  • K-Electric concerns about staff asking for cash: [email protected].

For other documents you may need, see online government services in Pakistan.

Checked October 2026. Meter prices and connection charges change, so no rupee figures are quoted as current.

Meter price and LESCO private-purchase details come from a press report, so confirm with your distribution company. Other sources: Power Division, K-Electric, MEPCO and NEPRA.

Frequently Asked Questions

How do I apply for a new electricity connection online in Pakistan?

Use the Electricity New Connection portal at enc.com.pk, choose your distribution company, fill in the form and upload your documents. In Karachi, apply through the K-Electric website, the KE Live app or a Customer Care Centre.

What documents do I need for a new electricity connection?

Usually an attested CNIC copy, proof of ownership or a tenancy agreement with the owner's NOC, an affidavit on stamp paper and, in many cases, a wiring test report. The exact list depends on your company and connection type.

What is a demand notice for an electricity connection?

It is a one-time payment document issued after your application is approved. It states what you must pay for items such as the security deposit, service connection and meter or line materials, and you pay it at a bank.

How long does it take to get a new meter?

K-Electric says a new connection can be energised within 15 days if all prerequisites are met, and longer for bigger loads. Distribution companies do not publish a single fixed time, and delays can occur during meter shortages.

How much does a new single-phase meter cost?

It varies by company, location, load and distance from the pole. The only safe figure is the one on your official demand notice, because news reports have shown large differences between areas and months.

Can a tenant apply for an electricity connection?

Often yes, but you will usually need the owner's NOC on stamp paper, signed before an oath commissioner, and a tenancy agreement. Check your company's requirement before applying.

Can I buy my own meter?

In October 2025, LESCO was reported to be allowing consumers to buy single-phase meters from approved manufacturers with a LESCO NOC. Ask your own company whether it has a similar policy before buying anything.

What if my application is delayed or rejected?

Ask the sub-division for the exact reason in writing, fix the problem and reapply or resubmit. If the delay continues, escalate to the company's complaint channels and then to NEPRA.

Where are the official time limits for new connections?

They are set in the NEPRA Consumer Service Manual, which has an annexure on the time frame for new connections. NEPRA approved a revised manual in 2025, so check the latest version on nepra.org.pk.

How we know this

  • Type Practical guide
  • Sources 5 (1 official/academic)
  • Reviewed October 2026
  • Disputed points None

Rules and fees change, confirm with the official links below before you act.

5 sources
  1. Ministry of Energy (Power Division), Government of Pakistan
  2. AASAAN Meter Below 80 KILOWATT FAQs, K-Electric
  3. Ease of Doing Business, Multan Electric Power Company
  4. Relief for Electricity Users as LESCO opens door to private purchases of single-phase meters, Pakistan Observer
  5. Consumer Service Manual (CSM) with amendments and clarifications, as on November 26, 2025, National Electric Power Regulatory Authority (NEPRA)
Suggest a correction

Stay updated

Stay Connected with DailyLife.pk

Get new travel guides, recipes and stories from across Pakistan, no spam, unsubscribe any time.

Your Pakistan journey starts here

From majestic mountains to vibrant cities, rich cuisine to timeless traditions — discover the real Pakistan with DailyLife.pk.